Puerto Rico Construction SWPPP

EPA is the construction stormwater permitting authority for the Commonwealth of Puerto Rico (permit PRR100000), handled by EPA Region 2’s Caribbean Environmental Protection Division.

Permit
EPA 2022 CGP, PRR100000
NOI timing
At least 14 calendar days before construction (NeT-CGP)
EPA office
Region 2, Caribbean Environmental Protection Division, Guaynabo
Inspections
Every 7 days, or every 14 days + within 24 hours of a 0.25 in. storm

What applies in Puerto Rico

Sites in Puerto Rico follow the standard 2022 CGP requirements below. The 2022 CGP Part 9 does not list additional Puerto Rico-specific conditions, but local permits from Puerto Rico agencies still apply to your project.

EPA’s construction inspection training, which qualifies inspectors under Part 6.3, is offered free in both English and Spanish.

Before you break ground

  1. Write the SWPPP first. EPA requires the SWPPP to be developed, consistent with Part 7 of the CGP, before you submit your Notice of Intent.
  2. File the NOI at least 14 calendar days before construction starts, through EPA’s electronic system (NeT-CGP). Coverage begins 14 calendar days after EPA notifies you it received a complete NOI, unless EPA delays or denies it.
  3. Install perimeter and other initial controls described in your SWPPP before earth-disturbing work.

Inspections

Under Part 4.2 you choose one of two schedules:

  • at least once every 7 calendar days, or
  • once every 14 calendar days and within 24 hours of a storm event producing 0.25 inches or more of rain in 24 hours.

Sites discharging to sediment- or nutrient-impaired or high-quality waters follow the increased frequency in Part 4.3, and stabilized areas can qualify for reduced frequency under Part 4.4. Inspections are only required during the site’s normal working hours.

Inspectors must be qualified under Part 6.3: complete EPA’s construction inspection course (free, in English and Spanish) or hold a current certification from a program covering the required topics.

Stabilization and dewatering

When work stops in an area for 14 or more calendar days, stabilization must start immediately and be completed as soon as practicable, no later than 14 calendar days after it begins (7 calendar days for sites discharging to certain sensitive or impaired waters). Arid, semi-arid and drought areas have their own schedule.

New in 2022: dewatering discharges to a sediment-impaired water or a Tier 2, 2.5 or 3 water need at least one turbidity sample per day of discharge from each discharge point, compared with a 50 NTU benchmark, with results reported quarterly in NeT-CGP.

Finishing the job

Submit a Notice of Termination within 30 calendar days after a Part 8.2 condition is met, such as final stabilization of the site or transfer of the site to another operator. Coverage ends at midnight of the day a complete NOT is submitted.

Heavy rain and inspections

If you choose the 14-day inspection schedule, every storm of 0.25 inches or more in 24 hours triggers an inspection within 24 hours. In a wet season that can mean more inspections than the fixed 7-day schedule, so pick the schedule that fits your rainfall.

Timing note: the 2022 CGP expires at 11:59 pm on February 16, 2027, and EPA published a proposed 2027 CGP on August 3, 2026. If your project will still be active after the 2022 permit expires, check EPA’s CGP page for how coverage moves to the new permit. We will update our template when the 2027 permit is final.

Frequently asked questions

How long before construction do I need to file?

File the NOI through NeT-CGP at least 14 calendar days before construction starts. Coverage begins 14 calendar days after EPA confirms it received a complete NOI, and the SWPPP must be written before you file.

How often do I have to inspect?

Either at least every 7 calendar days, or every 14 calendar days plus within 24 hours of a storm of 0.25 inches or more. Some sites must inspect more often (Part 4.3) and stabilized areas can inspect less often (Part 4.4).

Who can do the inspections?

A qualified person under Part 6.3: someone who completed EPA's free construction inspection course or holds a current certification from a program covering the required topics.

Is the EPA inspector training available in Spanish?

Yes. EPA's construction inspection training course is free and offered in English and Spanish.

Build your SWPPP binder

Answer plain-English jobsite questions, upload your site plan, and download an editable Word file plus one bookmarked PDF. $299 per site, paid only after your binder passes the readiness check.

Official sources

Last reviewed November 21, 2026. Summarized for planning; confirm current requirements with the permitting authority. This page is not legal or engineering advice.