How to Write a Construction SWPPP
A practical walk-through for contractors and engineers preparing a Stormwater Pollution Prevention Plan under EPA’s 2022 Construction General Permit. State permits follow a similar pattern; check your state’s page for differences.
1. Confirm which permit applies
Construction disturbing 1 acre or more, or less than 1 acre as part of a larger common plan of development, needs stormwater permit coverage. Whether you file with EPA or your state depends on location: EPA is the permitting authority in New Hampshire, Massachusetts, New Mexico, DC, Puerto Rico, the territories, much of Indian country and some federal facilities (full list). Most states run their own permit.
2. Gather site information
- Site address, latitude/longitude, total property area and the area you will disturb
- Receiving waters and whether they are impaired or high quality (Tier 2, 2.5 or 3); this changes inspection, stabilization and dewatering rules
- A site plan you can mark up: boundaries, disturbance areas, drainage, discharge points, surface waters and wetlands
- Every operator and contractor, with contact details and who controls what
- Construction phases with start and end dates
3. Write each part of the SWPPP
EPA’s SWPPP template, which Part 7 of the CGP is built around, is organized into these sections:
- Contact information and stormwater team, including who inspects and their training.
- Site evaluation and planning: project description, discharge information, construction sequence and dates, allowable non-stormwater discharges, and site maps.
- Other federal requirements: endangered species and historic property screening, and Safe Drinking Water Act underground injection where relevant.
- Erosion and sediment controls: buffers, perimeter controls, track-out, stockpiles, dust, steep slopes, topsoil, soil compaction, storm drain inlets, sediment basins, dewatering and stabilization.
- Pollution prevention: spill prevention, fueling, washing, storage of materials and wastes, concrete washout, fertilizers.
- Inspection, maintenance and corrective action procedures.
- Turbidity benchmark monitoring for dewatering, if it applies.
- Certification and notification, with appendices for maps, the NOI, inspection reports, training records and delegations.
4. Mind the deadlines
- The SWPPP must be developed before you submit the NOI.
- File the NOI at least 14 calendar days before construction (EPA CGP); coverage starts 14 days after EPA confirms receipt.
- Inspect every 7 days, or every 14 days plus within 24 hours of a 0.25-inch storm.
- Submit the Notice of Termination within 30 calendar days of final stabilization.
5. Common mistakes
- Leaving template instructions or placeholder brackets in the final document
- A site map that does not show discharge points, surface waters or control locations
- Missing signatures on certifications and delegation of authority
- An inspection schedule in the SWPPP that does not match what the crew actually does
- Not updating the SWPPP when the design, operators or controls change
Timing note: the 2022 CGP expires at 11:59 pm on February 16, 2027, and EPA published a proposed 2027 CGP on August 3, 2026. If your project will still be active after the 2022 permit expires, check EPA’s CGP page for how coverage moves to the new permit. We will update our template when the 2027 permit is final.
Frequently asked questions
Can I write a SWPPP myself?
Yes. The CGP does not require a SWPPP to be written by an engineer, though some projects and local agencies require a licensed professional's design or stamp for certain controls. You are responsible for its accuracy and for following it.
Do I have to use EPA's template?
No, but it is organized around the CGP's Part 7 requirements, which makes it easier to show you covered each one.
Build your SWPPP binder
Answer plain-English jobsite questions, upload your site plan, and download an editable Word file plus one bookmarked PDF. $299 per site, paid only after your binder passes the readiness check.
Official sources
- EPA: 2022 Construction General Permit
- EPA: Getting coverage under the CGP
- EPA: 2022 CGP permit text (as modified)
- EPA: Turbidity benchmark monitoring for dewatering
Last reviewed November 21, 2026. Summarized for planning; confirm current requirements with the permitting authority. This page is not legal or engineering advice.