Florida FDEP Construction Generic Permit

For Florida construction sites disturbing 1 acre or more (or part of a larger common plan of development) that discharge stormwater to surface waters or a municipal storm sewer system (MS4).

NOI fee
$250 (1 to under 5 acres) / $400 (5 acres or more)
NOI timing
At least 2 calendar days before construction starts
Inspections
Every 7 calendar days and within 24 hours of the end of a 0.50 in. storm
Records
Keep 3 years after final stabilization and NOT

What FDEP requires

  1. Develop the SWPPP before you submit the NOI (Parts 2.2 and 4.3), following standard industry practices (Part 4.2).
  2. Submit the NOI and fee at least 2 calendar days before construction begins: $250 for 1 to under 5 acres, $400 for 5 acres or more (Rule 62-4.050).
  3. Install perimeter controls before construction starts if your SWPPP calls for them.
  4. Have a qualified inspector inspect at least every 7 calendar days and within 24 hours of the end of a 0.50-inch storm, including weekends and holidays (Part 6.1).

What the SWPPP must contain (Table 4.7.1)

  • Stormwater team, including the qualified inspector, with responsibilities
  • All contractors and subcontractors and the areas they work in
  • Description and sequence of construction, with start and end dates of major activities
  • Total site area and disturbed area, soil data, and each discharge point’s latitude/longitude, drainage area and receiving water or MS4
  • Site map with boundaries, entrances, disturbance areas, drainage patterns, controls, stabilization areas, surface waters and wetlands
  • Non-stormwater discharges, dewatering controls, BMPs, permanent stormwater controls and maintenance
  • Signed certifications from every contractor and subcontractor

Florida-specific signatures and records

Every contractor and subcontractor named in the SWPPP signs FDEP’s certification statement (Part 4.6) before working on site. Keep the NOI, FDEP’s acknowledgement letter, the SWPPP, inspection reports and FDEP notices for three years after final stabilization and the Notice of Termination (Part 4.4). Update the SWPPP within seven calendar days of significant changes (Part 4.5).

Report a discharge that may endanger health or the environment to the State Warning Point (800-320-0519 or 850-413-9911) within 24 hours.

Your SWPPPBinder binder in Florida

FDEP lets the SWPPP follow standard industry practice, so the binder uses the EPA 2022 CGP template structure with Florida’s trigger, fee and inspection rules applied, plus a Florida supplement page: the Part 4.6 certification wording with a signature table pre-filled from your contractors, record keeping and State Warning Point reporting.

FDEP has posted a draft of an updated construction generic permit; we will update the binder if the adopted version changes these requirements.

Frequently asked questions

How much is the Florida construction NOI fee?

$250 for sites disturbing 1 acre to under 5 acres and $400 for 5 acres or more, under Rule 62-4.050 F.A.C.

How early must I file the NOI in Florida?

At least 2 calendar days before construction begins, with the SWPPP already developed.

How often must a Florida site be inspected?

At least once every 7 calendar days and within 24 hours of the end of a storm of 0.50 inches or more, even on weekends and holidays, by a qualified inspector.

Build your SWPPP binder

Answer plain-English jobsite questions, upload your site plan, and download an editable Word file plus one bookmarked PDF. $299 per site, paid only after your binder passes the readiness check.

Official sources

Last reviewed November 21, 2026. Summarized for planning; confirm current requirements with the permitting authority. This page is not legal or engineering advice.