SWPPP Inspection Requirements and Schedules
Inspection frequency is the requirement crews most often get wrong. Here is what EPA’s 2022 CGP and Florida’s construction generic permit actually say.
EPA 2022 CGP: choose one schedule
- Option 1: at least once every 7 calendar days.
- Option 2: once every 14 calendar days and within 24 hours of a storm producing 0.25 inches or more of rain within 24 hours.
“Within 24 hours” runs continuously from when the trigger occurs. Inspections are only required during normal working hours. Sites discharging to sediment- or nutrient-impaired or high-quality waters follow the increased schedule in Part 4.3.
Reduced frequency for stabilized areas
Where the stabilization steps in Part 2.2.14a are complete, you can reduce inspections in that area to twice in the first month (no more than 14 calendar days apart), then once a month until coverage ends. If work resumes there, the normal frequency applies again immediately. Record the start and end of the reduced period in the SWPPP.
Florida FDEP permit
Florida does not offer the 14-day option: inspect at least once every 7 calendar days and within 24 hours of the end of a storm of 0.50 inches or more, including weekends and holidays, using a qualified inspector you provide (Part 6.1). See the Florida page.
Who can inspect
Under CGP Part 6.3, the inspector must have completed EPA’s construction inspection training (free, English and Spanish) or hold a current certification from a program covering the required topics. EPA lists examples of such programs without endorsing them.
What a good inspection covers
- All disturbed areas, stockpiles, and areas used for storage of materials
- Every erosion and sediment control and pollution prevention practice, and whether it needs maintenance
- Discharge points and nearby surface waters, looking for sediment or other pollutants
- Locations where vehicles leave the site, for track-out
- Any condition needing corrective action, with the date it was found and fixed
Keep the paper trail
Record each inspection on the day it happens, sign it, and keep it with the SWPPP. If you choose the rain-triggered schedule, keep the rain-gauge readings that show when inspections were triggered.
Frequently asked questions
Do I have to inspect on weekends?
Under the EPA CGP, inspections are only required during normal working hours. Florida's permit explicitly requires the 24-hour post-storm inspection even when it rains on a weekend or holiday.
Which EPA schedule should I choose?
The 7-day schedule is predictable. The 14-day schedule means fewer routine inspections but adds one within 24 hours of every storm of 0.25 inches or more, which can mean more inspections in a wet season.
Build your SWPPP binder
Answer plain-English jobsite questions, upload your site plan, and download an editable Word file plus one bookmarked PDF. $299 per site, paid only after your binder passes the readiness check.
Official sources
- EPA: 2022 CGP permit text (as modified)
- EPA: CGP inspector training
- FDEP: Construction activity stormwater
Last reviewed November 21, 2026. Summarized for planning; confirm current requirements with the permitting authority. This page is not legal or engineering advice.