New Mexico Construction SWPPP

EPA is the construction stormwater permitting authority in New Mexico (permit NMR100000, except Indian country), with New Mexico conditions in Part 9 of the 2022 CGP.

Permit
EPA 2022 CGP, NMR100000
NOI timing
At least 14 calendar days before construction (NeT-CGP)
Key limit
No CGP coverage for discharges to ONRWs (Tier 3 waters)
Inspections
Every 7 days, or every 14 days + within 24 hours of a 0.25 in. storm

New Mexico conditions in Part 9 of the CGP

  • Outstanding National Resource Waters: operators are not eligible for CGP coverage for discharges to ONRWs listed in 20.6.4.9 NMAC (Tier 3 waters). Those projects need an NPDES individual permit from EPA and must meet 20.6.4.8(A) NMAC.
  • Emergency exception: work responding to a public emergency (for example wildfire or extreme flooding) can proceed, with notice to the New Mexico Environment Department within seven days of starting and a summary within 30 days.
  • Indian country in New Mexico is covered by separate EPA permits (for example Navajo lands under the Arizona permit and Ute Mountain lands under the Colorado permit).

Before you break ground

  1. Write the SWPPP first. EPA requires the SWPPP to be developed, consistent with Part 7 of the CGP, before you submit your Notice of Intent.
  2. File the NOI at least 14 calendar days before construction starts, through EPA’s electronic system (NeT-CGP). Coverage begins 14 calendar days after EPA notifies you it received a complete NOI, unless EPA delays or denies it.
  3. Install perimeter and other initial controls described in your SWPPP before earth-disturbing work.

Inspections

Under Part 4.2 you choose one of two schedules:

  • at least once every 7 calendar days, or
  • once every 14 calendar days and within 24 hours of a storm event producing 0.25 inches or more of rain in 24 hours.

Sites discharging to sediment- or nutrient-impaired or high-quality waters follow the increased frequency in Part 4.3, and stabilized areas can qualify for reduced frequency under Part 4.4. Inspections are only required during the site’s normal working hours.

Inspectors must be qualified under Part 6.3: complete EPA’s construction inspection course (free, in English and Spanish) or hold a current certification from a program covering the required topics.

Stabilization and dewatering

When work stops in an area for 14 or more calendar days, stabilization must start immediately and be completed as soon as practicable, no later than 14 calendar days after it begins (7 calendar days for sites discharging to certain sensitive or impaired waters). Arid, semi-arid and drought areas have their own schedule.

New in 2022: dewatering discharges to a sediment-impaired water or a Tier 2, 2.5 or 3 water need at least one turbidity sample per day of discharge from each discharge point, compared with a 50 NTU benchmark, with results reported quarterly in NeT-CGP.

Finishing the job

Submit a Notice of Termination within 30 calendar days after a Part 8.2 condition is met, such as final stabilization of the site or transfer of the site to another operator. Coverage ends at midnight of the day a complete NOT is submitted.

Dry-climate scheduling

Much of New Mexico is arid or semi-arid as the CGP defines it. The permit has its own stabilization schedule for those areas during the seasonally dry period. Our permit checker flags arid and semi-arid ZIP codes and their dry months so you can plan.

Timing note: the 2022 CGP expires at 11:59 pm on February 16, 2027, and EPA published a proposed 2027 CGP on August 3, 2026. If your project will still be active after the 2022 permit expires, check EPA’s CGP page for how coverage moves to the new permit. We will update our template when the 2027 permit is final.

Frequently asked questions

How long before construction do I need to file?

File the NOI through NeT-CGP at least 14 calendar days before construction starts. Coverage begins 14 calendar days after EPA confirms it received a complete NOI, and the SWPPP must be written before you file.

How often do I have to inspect?

Either at least every 7 calendar days, or every 14 calendar days plus within 24 hours of a storm of 0.25 inches or more. Some sites must inspect more often (Part 4.3) and stabilized areas can inspect less often (Part 4.4).

Who can do the inspections?

A qualified person under Part 6.3: someone who completed EPA's free construction inspection course or holds a current certification from a program covering the required topics.

Can I use the CGP if my site drains to an Outstanding National Resource Water?

No. In New Mexico, discharges to ONRWs (Tier 3 waters) are not eligible for the CGP except for public-emergency work; you need an NPDES individual permit from EPA.

Build your SWPPP binder

Answer plain-English jobsite questions, upload your site plan, and download an editable Word file plus one bookmarked PDF. $299 per site, paid only after your binder passes the readiness check.

Official sources

Last reviewed November 21, 2026. Summarized for planning; confirm current requirements with the permitting authority. This page is not legal or engineering advice.