EPA 2022 Construction General Permit (CGP)
For construction sites disturbing 1 acre or more (or part of a larger common plan) in areas where EPA, not the state, is the stormwater permitting authority.
- Permitting authority
- U.S. EPA (NeT-CGP for NOI, NOT and reports)
- NOI timing
- At least 14 calendar days before construction starts
- Inspections
- Every 7 days, or every 14 days + within 24 hours of a 0.25 in. storm
- Permit term
- 2022 CGP expires 11:59 pm, February 16, 2027
Where the EPA CGP applies
EPA issues construction stormwater coverage directly in these areas (Appendix B of the 2022 CGP):
- New Hampshire, Massachusetts (except Indian country), New Mexico (except Indian country covered by other EPA permits), the District of Columbia and Puerto Rico;
- Guam, American Samoa, the Northern Mariana Islands, Johnston Atoll, and Midway and Wake Islands;
- Indian country in many states, where no EPA-approved program covers it;
- federal facilities in Colorado, Delaware and Vermont, federal operators in Washington, and listed Lands of Exclusive Federal Jurisdiction.
Everywhere else, the state issues its own construction general permit (for example Florida).
Before you break ground
- Write the SWPPP first. EPA requires the SWPPP to be developed, consistent with Part 7 of the CGP, before you submit your Notice of Intent.
- File the NOI at least 14 calendar days before construction starts, through EPA’s electronic system (NeT-CGP). Coverage begins 14 calendar days after EPA notifies you it received a complete NOI, unless EPA delays or denies it.
- Install perimeter and other initial controls described in your SWPPP before earth-disturbing work.
Inspections
Under Part 4.2 you choose one of two schedules:
- at least once every 7 calendar days, or
- once every 14 calendar days and within 24 hours of a storm event producing 0.25 inches or more of rain in 24 hours.
Sites discharging to sediment- or nutrient-impaired or high-quality waters follow the increased frequency in Part 4.3, and stabilized areas can qualify for reduced frequency under Part 4.4. Inspections are only required during the site’s normal working hours.
Inspectors must be qualified under Part 6.3: complete EPA’s construction inspection course (free, in English and Spanish) or hold a current certification from a program covering the required topics.
Stabilization and dewatering
When work stops in an area for 14 or more calendar days, stabilization must start immediately and be completed as soon as practicable, no later than 14 calendar days after it begins (7 calendar days for sites discharging to certain sensitive or impaired waters). Arid, semi-arid and drought areas have their own schedule.
New in 2022: dewatering discharges to a sediment-impaired water or a Tier 2, 2.5 or 3 water need at least one turbidity sample per day of discharge from each discharge point, compared with a 50 NTU benchmark, with results reported quarterly in NeT-CGP.
Finishing the job
Submit a Notice of Termination within 30 calendar days after a Part 8.2 condition is met, such as final stabilization of the site or transfer of the site to another operator. Coverage ends at midnight of the day a complete NOT is submitted.
Your SWPPPBinder binder
We build on EPA’s own 2022 CGP SWPPP template, fill it from plain-English jobsite answers, merge your site map and appendices into one bookmarked PDF, and give you the editable Word file. You review it, add site-specific details, and sign the certifications. Part 9 adds state-specific conditions for some areas; the state pages above list them.
Timing note: the 2022 CGP expires at 11:59 pm on February 16, 2027, and EPA published a proposed 2027 CGP on August 3, 2026. If your project will still be active after the 2022 permit expires, check EPA’s CGP page for how coverage moves to the new permit. We will update our template when the 2027 permit is final.
Frequently asked questions
How long before construction do I need to file?
File the NOI through NeT-CGP at least 14 calendar days before construction starts. Coverage begins 14 calendar days after EPA confirms it received a complete NOI, and the SWPPP must be written before you file.
How often do I have to inspect?
Either at least every 7 calendar days, or every 14 calendar days plus within 24 hours of a storm of 0.25 inches or more. Some sites must inspect more often (Part 4.3) and stabilized areas can inspect less often (Part 4.4).
Who can do the inspections?
A qualified person under Part 6.3: someone who completed EPA's free construction inspection course or holds a current certification from a program covering the required topics.
Is there a fee for EPA CGP coverage?
The 2022 CGP itself does not set an NOI fee. Some states and localities add their own permits with fees, such as New Hampshire's Alteration of Terrain permit.
Build your SWPPP binder
Answer plain-English jobsite questions, upload your site plan, and download an editable Word file plus one bookmarked PDF. $299 per site, paid only after your binder passes the readiness check.
Official sources
- EPA: 2022 Construction General Permit
- EPA: Getting coverage under the CGP
- EPA: Submitting an NOI, NOT or LEW (NeT-CGP)
- EPA: CGP inspector training
- EPA: Turbidity benchmark monitoring for dewatering
- EPA: 2022 CGP permit text (as modified)
- EPA: 2022 CGP Appendix B, areas of coverage
Last reviewed November 21, 2026. Summarized for planning; confirm current requirements with the permitting authority. This page is not legal or engineering advice.